Court Rebuild Schedule(tentative)
April 11-15 Install Base, set sono tubes, install granular
April 18-21 Install granular
April 25-29 Buffer week
May 2-6 Install fence and net post sleeves
May 9-13 Fine grade, pave
May 16-20 Asphalt cure
May 23-27 Asphalt cure, install lighting
May 30- June 3 Asphalt cure, install fencing
June 6-10 Surface/paint courts
June 13-17 Surface/paint courts
June 20 Clean courts
June 21 Play on courts
The above is the current tentative schedule and is subject to change based on weather